Lesson 10 of 10 · 6 min
How a BESS project happens
- Know the 6 steps from survey to monitoring
1) Site survey 2) Design and sizing 3) Approvals (DISCOM, inspector, society NOC) 4) Installation 5) Testing and commissioning 6) Remote monitoring and maintenance.
A small home system takes 2–4 weeks; a society or factory 1–3 months.
India note
India example: Saksham Solar's typical society project: survey in week 1, approvals weeks 2–5, install week 6.
Key takeaways
- Always start with a survey
- Approvals take time
- Monitoring continues for years