Lesson 10 of 10 · 6 min

How a BESS project happens

  • Know the 6 steps from survey to monitoring

1) Site survey 2) Design and sizing 3) Approvals (DISCOM, inspector, society NOC) 4) Installation 5) Testing and commissioning 6) Remote monitoring and maintenance.

A small home system takes 2–4 weeks; a society or factory 1–3 months.

India note

India example: Saksham Solar's typical society project: survey in week 1, approvals weeks 2–5, install week 6.

Key takeaways

  • Always start with a survey
  • Approvals take time
  • Monitoring continues for years
Open the sizing calculator

Quick quiz

1. First step?
2. Commissioning means…
3. After handover comes…