Testing and commissioning (FAT, SAT)

  • Run a capacity test

FAT at the factory checks build quality. SAT on site checks wiring, protection, communications and functions. Capacity test: full charge, discharge at rated power to cutoff, measure kWh and RTE.

India note

India example: A 215 kWh unit delivered 196 kWh AC — matching its usable spec.

Key takeaways

  • FAT at factory
  • SAT on site
  • Measure usable kWh

Quick quiz

1. SAT happens…
2. Capacity test measures…
3. RTE = …